Pre-bid brief · Live RFP · Under NDA

A prime's pre-bid brief for Escondido RFP No. 26-19.

City of Escondido, as-needed geotechnical and special inspection services for the Utilities CIP. The prime owns the field, Techtiz builds the paperwork engine.

Live · closes Jun 18, 2 PM PDT
City of Escondido
Awarding body City of Escondido
Jurisdiction California
Status Responding under NDA
Solicitation
RFP No. 26-19As-needed, task-order
Scope
Utilities CIPGeotech & special inspection
Instrument cap
NTE $100,000Across four years
Techtiz role
Back-officeNDA-first, never agency-facing
Schedule of events

One hard close, no cure.

A single proposal email to Randy Manns, cc Cricket Lichtenfels, by the deadline. Late electronic submissions are not accepted and there is no cure.

  1. Published

    RFP No. 26-19 released

  2. Questions due

    2:00 PM PDT

  3. Answers posted

    City responds to questions

  4. Proposals due, 2 PM PDT

    Single email. No late acceptance

  5. Staff review

    City evaluates proposals

  6. Award

    Council or designee approves

Best value, not low price. The clock is running.

The award model

As-needed, multiple-award, no guaranteed minimum.

The City may select one firm or split work across two. A single task order's $100,000 can be divided between two consultants. Funding is fiscal-year based and subject to annual appropriation.

StructureNon-exclusive, task-order based. One or more consultants at the City's discretion, with no guaranteed minimum volume.
The instrumentA single agreement is not-to-exceed $100,000, and that ceiling covers all four years. It is a cap on one instrument, not on the relationship.
The real prizeThe on-call relationship: an initial term through July 31, 2027, plus three optional one-year extensions through July 2030.
RatesFixed for the term once submitted. There is no adjustment mechanism without a written amendment.
Scope · The differentiator
The daily report and RFI responses are liability-grade construction-administration records, not courtesy updates.

Under Attachment A, the C.5 daily report and C.2 RFI responses are what the City's construction manager uses to track compaction data, document contractor performance, and mitigate claims. A credible bid treats the documentation as the deliverable it is.

This documentation backbone is exactly what Techtiz compiles and formats behind the prime, after the field data is collected and certified.
Task allocation

What a remote back-office can build, and what stays on-site.

The boundary that makes a compliant Subcontracting model work on a licensed field-services contract.

Two bars, both honest. A practical and regulatory bar: field tasks need on-site, California-licensed, ICC-certified, nuclear-gauge-authorized staff under CBC Chapter 17, DIR, and IRCA, so an offshore team cannot perform them at all. A contractual gate: the anti-assignment and personnel-lock clauses require prior written City consent before any subcontracting, and City-provided materials become City property immediately.

Remote back-office Subcontracting
Under NDA and written consent

Draft the Executive Summary narrative for the prime's review

Compile and format the five-project reference table from prime records

Format key-personnel resumes to the Attachment A categories

Build the rate-schedule template, all four components pre-labeled

Prepare the Noncollusion Declaration fields for the prime to sign

Assemble the final proposal document for the prime to review and email

After award, draft RFI technical responses for the PE to certify

Compile and format daily reports from prime-collected field data

Format lab and field test reports for the PM to submit

Draft invoices for the prime to submit

Techtiz operates only in this column, behind the prime, under NDA and written consent.
US prime only
On-site, licensed, signed

All on-site field recommendations and construction-meeting attendance

Special inspection of reinforced concrete

Trench backfill and compaction testing

Real-time deficiency notification

PE review and certification of every result

Signing and submitting the Noncollusion Declaration

Submitting all reports and invoices to the City

Custody of City as-builts, records, and raw lab data

Gates, stated plainly. A signed NDA before any City document moves. No storage of City materials on servers outside the United States without written City consent. The offshore role is a written subcontract to the US prime, with City consent obtained before any work is assigned. Pre-award support is the default lane, any post-award involvement is administrative and non-field only.

Where bids fail

Seven ways a strong firm loses this one.

None is about engineering skill. Each is a procurement or contract trap.

Single-channel communication Before award

The rule

No contact with any City employee other than Randy Manns, with cc to Cricket Lichtenfels, before award.

If you miss it

Contacting anyone else is grounds for rejection. Route every question through the one channel.

How scoring works

Best value, not low price.

Seventy percent of the score is qualifications, experience, and references. Cost is only fifteen. The City also reserves a discretionary, unweighted interview right.

Scoring weights, out of 100

Key Personnel qualifications25%
Relevant project experience25%
Company qualifications & experience20%
References15%
Cost reasonableness of rate schedule15%
Value & pricing

A rate-schedule competition, fixed for the term.

Time and materials, not a lump sum. Rates lock once submitted. The field technician and special inspector rates are the variable that most affects the win, since those roles are used most. Tender Insight estimates.

Low
$75/ hr field tech

Special inspector $80, PE $145.

MidRecommended
$85/ hr field tech

Special inspector $90, PE $160, PM $175. Model under NDA

High
$100/ hr field tech

Special inspector $110, PE $185.

Mid is the recommended posture because cost carries only 15 percent. Pricing the most-used roles competitively matters more than shaving the PE rate.
Compliance frameworks

The statutes the contract pulls in.

California law, SD venue

San Diego County courts. Government Claims Act applies.

Prevailing wages & DIR

Labor Code 1720, 1770; DIR registration under 1725.5.

IRCA

Work-authorization compliance for all staff.

CBC Chapter 17

Governs special inspection on this work.

RWQCB storm-water permit

Order R9-2013-0001, through the indemnification clause.

Buyer's NIGP codes

92546, 92550, 92532, 95826, 91275.

Agency context

Who is buying, and why.

The City of Escondido is an incorporated Council-Manager city in North County, San Diego County, incorporated 1888. The Utilities Department runs the capital program this RFP supports, across water, wastewater, recycled water, and stormwater infrastructure.

Escondido City Hall

The City of Escondido is an incorporated Council-Manager city in North County, San Diego County, incorporated 1888. The Utilities Department runs the capital program this RFP supports, across water, wastewater, recycled water, and stormwater infrastructure.

~151,000
Residents, public-source estimate
4th
Most populous in San Diego County

Escondido City Hall. Photo: Mark Skovorodko, CC BY-SA 4.0, via Wikimedia Commons.

The competing field

47 primes mapped, a long tail of boutiques.

From the prime-contractor database. A handful of national firms anchor the field, but most of the bench is mid-market and boutique shops that compete on fit. Figures are public-source estimates for partner targeting.

47
Firms mapped to the solicitation
16/ 31
Highly / partially relevant
5
California-based primes
~$8.7B
Combined estimated revenue
10national, $100M+, where the revenue concentrates21mid-market, $10M to $100M16boutique, under $10M
The named company-level map, contacts, and relevance scoring are in the full document pack. Ask us for it under NDA.
Before June 12

Four questions worth filing.

Questions the prime should consider, through the one channel. Techtiz never contacts the City.

Question 01

How are resumes counted against the 20-page limit?

Page-limit treatment of resumes and appendices changes how the package is built.

Question 02

Is a two-firm prime and sub arrangement acceptable?

The split-award language hints at it. Confirm before structuring the team.

Question 03

Does DIR registration apply to inspection services here?

Clarify the prevailing-wage and DIR scope for this specific work.

Under NDA
Question 04

Is a debrief available to unsuccessful proposers?

Useful for the next pursuit, and a legitimate pre-bid ask.

Under NDA
How Techtiz fits

The paperwork engine, behind your firm.

Techtiz builds the documentation. The prime owns the field, the agency relationship, and every signature. We never contact the City.

NDA before any data

A mutual NDA and written City consent before a single City document moves.

Pre-award package

Executive summary, references, resumes, and rate schedule, assembled for your review.

Post-award paperwork

RFI drafts, daily reports, and test-report formatting, after your licensed staff certify.

Your firm owns the field

All on-site work, certification, signatures, and City communication stay with the prime.

NDA Prime name, engagement value, and City data stay under NDA. Techtiz never contacts the City.
Bidding RFP No. 26-19? The window is open.

Request the full RFP-decode pack.

A US partner manager replies within one business day, under a mutual NDA, never agency-facing. Your firm holds the field, the certifications, and the City relationship.

Frequently asked questions

Pre-bid brief & confidentiality

Quick answers about how to use this engagement example and what detail is available under NDA.

Why is the prime contractor name withheld?

Most SLED subcontract work sits under mutual NDA and prime branding requirements. Public summaries describe engagement type, technical surface, and outcomes. Partner names and proposal content are shared only with explicit written permission or under an executed teaming agreement.

Can Techtiz support our bid on a similar pursuit?

Yes. If your pursuit matches this engagement type, email sled@techtiz.co or use the teaming intake form. Within 1 business day a U.S.-based partner manager replies with a mutual NDA template and a calendar slot—never agency-facing.

What do we receive under NDA?

Full RFP-decode packs, compliance matrices, technical volumes, submission runbooks, and named-resume options scoped to your vehicle and timeline. Prime name, pricing, and agency data stay inside the prime boundary.

Does Techtiz contact the procuring agency?

No. Techtiz is subcontract-only and never faces the agency. Your program manager holds the client relationship, sign-off, and all agency communication.